Construction Submittal Log Template

Opening local draft…

What should a construction submittal log template track?

Use one row per product data package, shop drawing, or sample. Record the spec section and item, the review status, procurement lead time in whole days, and the reviewer’s name, review date, and notes.

What do Approved, Revise & Resubmit, and Pending mean in the log?

Use Approved when the reviewer accepts the submittal. Use Revise & Resubmit when corrections and another review are required. Use Pending when a decision is outstanding, and record review instructions in the notes.

How should I record lead time in a submittal log?

Enter the expected order-to-delivery duration in whole days. Record the vendor’s assumptions, any approval dependency, and confirmed delivery dates in the reviewer notes.

Can I export the construction submittal log to PDF and CSV?

The verification rows update the live closeout preview as you edit. A Job Pass or Pro unlocks the clean PDF and the audit CSV, with one spreadsheet record per submittal and separate columns for review and lead-time details.